19:04 03 Oct 24
Publication of one JI monitoring report and one JI verification report
Publication of one JI monitoring report and one JI verification report
Publication of one JI monitoring report This message is to notify you that an accredited independent entity (AIE) submitted to the UNFCCC secretariat a monitoring report for the following joint implementation (JI) project: "0173. Mockiai Wind Power Joint Implementation Project" with the monitoring report number "003", covering the period from 01 October 2012 to 31 December 2012. The abovementioned monitoring report is now available on the UNFCCC JI website under <http://ji.unfccc.int/JI_Projects/DeterAndVerif/Verif/MonRep.html>. Paragraph 36 of the annex to decision 9/CMP.1 (JI guidelines) stipulates that, under the verification procedure under the Joint Implementation Supervisory Committee (Track 2 procedure), reports on reductions in emissions by sources or enhancements of removals by sinks due to JI projects shall be made publicly available. Publication of one JI verification report In accordance with paragraph 38 of the JI guidelines, a verification pertaining to the following JI project, for monitoring report number "004" covering the period from 14 October 2012 to 31 December 2012, has been submitted by an AIE to the secretariat and will be publicly available as of tomorrow, 09 March 2013: "0064. Nitrous Oxide Emission Reduction Project at GP Nitric Acid Plant in AB Achema Fertiliser Factory" The period for requesting a review will end on 23 March 2013 (17:00 GMT). The abovementioned verification will be available on the UNFCCC JI website under <http://ji.unfccc.int/JI_Projects/DeterAndVerif/Verif/VerifRep.html>. Paragraph 38 of the annex to decision 9/CMP.1 (JI guidelines) stipulates that, under the verification procedure under the JISC, the AIE shall make its verification publicly available through the secretariat, together with an explanation of its reasons. In accordance with paragraph 39 of the JI guidelines, a verification shall be deemed final 15 days after the date on which it is made public, unless a Party involved in the project or three JISC members request a review. |
Connect with JI: